Friday, January 13, 2017

Construction Update

Hello Friends of Scouting!

We hope you had a great holiday and are ready to get back to Scouting!!!!

Lots of construction has taken place since the last post.  The new flooring in the hallway and main business area has been installed.  The paint is all done throughout the new areas.  The heaters are installed in the Warehouse and all the security systems are back working.

We have a new water heater that actually puts out hot water and the biggest item that is really noticeable is the new building has new stonework that matches the existing stonework that's been on for 30 plus years.

We are looking at the first week of February to be done with Phase 1 and we are looking forward to that!

Main business area with the two new offices on the right

The District Executive Office area

New Water Heater

New IT Room



Happy Scouting!
 