Construction Update

Friends of Scouting,


Lots of progress at the Scout Office over the past few weeks.  The parking lot is ready to be asphalted. The new Air Conditioning/Heating units are in, the Scout Shop area is coming together nicely, and the bathrooms are being tiled!


The new ceiling grid and tiles are going up this week and the walls have the initial coat of paint and texture.  Even the new security cages are installed!


We are looking at the end of May before we are ready to make the move and we can't wait to show this place off!


New patio area (we saved the tree!)

Parking lot

More parking lot!

Framing for the new patio

First concrete pour